Production Impact Testing

Do you know vessel manufacturers produce Production Impact Test Weld Coupons? Production impact testing is fairly common for vessels with shell walls greater than 1.5” in thickness. Production impact testing ensures that the actual production materials, including weld metal, have the proper toughness requirements to meet ASME Code and applicable specifications that apply to your job.

  • The rules for production impact testing can be found in ASME Section VIII, UG-84 (i). Below are just a few of the requirements that have to be followed before and during the production impact testing welding process.
  • The vessel impact test plate shall be from one of the heats of steel used for the vessel or group of vessels
  • For Category A joints (longitudinal seams), the test plate shall, where practicable, be welded as an extension to the end of a production joint so that the test plate weldment will represent as nearly as practicable the quality and type of welding in the vessel joint.
  • For Category B joints (girth seams) that are welded using a different welding procedure than used on Category A joints, a test plate shall be welded under the production welding conditions used for the vessel, using the same type of equipment and at the same location and using the same procedures as used for the joint, and it shall be welded concurrently with the production welds or as close to the start of production welding as practicable.

The attached pictures in this newsletter are actual examples of what a production impact test plate can look like. In these examples, the test plate is of the same heat as the vessel. The joint design of the test plate matches the joint design of the vessel long seam. The welder or welding operator will start welding the long seam, and as an extension of the long seam, the welder or welding operator will weld the test plate with the same WPS and welding consumables used for the production joint. Once the joint and the test plate are welded, the test plate is Charpy V notched tested for toughness. The condition of the test plate (PWHT, MDMT, mechanical requirements), should be the same as the vessel requirements.

Question: What if my vessel requires production impact testing, but my company isn’t rolling and welding the long seams? What if we are buying our shells rolled and welded from another company?

Answer: In this case, you need to make sure that the company that is performing the welding on the long seams is aware that the vessel requires production impact testing. They will be responsible for performing the production impact testing for the long seams that they are welding. They will need to supply you with all of the applicable testing reports. Once you are ready to start welding the girth seams, you will also need to run a production impact test with the WPS you are using for production welding.

Question: How do I know if my weld metal will meet the toughness requirements at the test temperature and for the MDMT of the vessel?

Answer: You should always check the manufacturer’s recommendations and certificate of conformance or the MTR’s for the welding consumables. You can also check the classification of the welding consumable in the appropriate specification in ASME Section II Part C. Make sure that the welding consumables used in production meet the requirements of the production vessel.

BOARDMAN’S ENGINEERING SEMINAR

We are excited to be able to be hosting our 6th annual engineering seminar on April 19-20. We are excited about the 22 customers coming to Boardman for this course. It’s a great opportunity to learn more about ASME Section VIII Div I code, and fabrication, and have an opportunity to weld and network with other engineers around the country. During our next quarterly newsletter, we’ll share some of the feedback from our 2022 seminar. If you are interested in attending our 2023 course, please let us know.

“The experience that Boardman and the instructor bring to the classroom is incredibly valuable. This course was worth every second of my time and I will be recommending it to all of my colleagues.”

BOARDMAN NEWSLETTER:

We have appreciated the positive feedback on the newsletter we’ve sent out over the years. We want to continue building strong relationships with our customers and be a resource as the experts in pressure vessel fabrication. We hope you find this newsletter beneficial as we share tips on the pressure vessel design and construction process. If there are any topics you would like us to address, please let us know!

Definitely a great team effort between HFS and Boardman to get this knocked out quickly with no mistakes.  Appreciate you and your teams help getting this across the finish line!

Reliability & Inspection

HF Sinclair

The BFS team is very responsive, conduct quality work, and produce detailed reports.  They have excellent level of support, responsiveness and quality work!

Construction Manager

Vestas

“I am glad you guys do the newsletters. Educate AND do the work. Most don’t do this. It is similar to what Dave Ramsay says about looking for a Financial Advisor… look for one with a heart of a teacher.”

Equipment Engineer

Fluor

“I would like to go out of my way to say this is the quickest I have seen a vessel come together. Your ability to manage this on such short notice does not go unnoticed and definitely will earn you some more business. Your professional approach and ability to keep this moving was amazing! I was hoping to see this thing through to the end and see about getting some Guiness world record trophy on our walls.”

Mechanical Engineer

Chevron

“Just wanted to send a quick thank you for sending these newsletters. I really enjoy them and share them with others at the office.”

Project Management

Kestrel Engineering

“Thank you for all your help on this order. Please let your team know that everything Boardman has done for this order has been top notch!”

Mechanical Engineer

Worley

“It was a real pleasure working with you and your team. I wish all vendors would have the same high quality team!”

Expeditor

Worley

“Your engineering team has gone above and beyond for our current projects. We have thrown quite a few changes at them and they have dug into code details that are not normally required to satisfy the requests of some of our SME folks. They are always available, even when they’re off or on weekends to help answer any urgent questions. I tried to find something we can do to help recognize the extra efforts, but could not come up with anything. Thank you for the efforts and willingness to work with us so closely on these urgent jobs.”

Mechanical Engineer

Chevron

“It was great pleasure and it was sure a huge effort pulled by Boardman organization. Promoting such events are very helpful to the engineering community in general but very few places realize the same. Boardman being exceptional and very hospitable place to be for this event. I want to say Thank You Boardman!”

Mechanical Engineer

Chevron

“The class was an excellent use of time and has increased my industry knowledge. Good mix of both end user and design engineer attendance which drove discussions into new directions. I will highly recommend to my firm for attendance next year.”

Mechanical Engineer

S&B Engineering

“Thank you and everyone at Boardman for an excellent 2 days of training and exceptional hospitality. While it gave me the opportunity to get out of the office for 2 days, it was also a great training/refreshing opportunity for me and on top of it, I got to visit your facility, which I think is quite impressive. Hope to have some more work in your shop soon. There are several folks here who were amazed when I told them that you guys had welding stations set up and each of us got to weld and try out as many as 4 welding processes. Please keep me posted on the next training session.”

Vessel Engineer

Burns & McDonnell

“I just wanted to say thank you very much to you and your team for all of the work that you put in to make this seminar possible. I was very impressed with the quality of the seminar. It is the best technical seminars I have been to. The classroom intermixed with shop time made the experience a one of a kind. The instructor is a wealth of knowledge. I was also very impressed with the care and concern that you had for those attending. You guys have superb customer service. I really appreciate the opportunity and it means a lot.”

Mechanical Engineer

MKEC Engineering

“Thank you guys very much for putting together the Pressure Vessel Fabrication presentation. I’ve heard great things from about the vessels currently in your shop. We look forward to building a long lasting relationship.”

Corrosion/Materials Engineer

Phillips 66

“The Boardman team’s expertise, experience and processes made our project easy. The communication between their team and mine ensured our project ran smoothly. I knew I could count on the work they sent. I look forward to working with a company that communicates well and takes pride in their work.”

Mechanical Engineer

Worley

“I just wanted to share some photos of the Deisobutonizer being lifted into place yesterday. None of this would have been possible without your efforts in both the manufacturing and transport of the tower. This is the largest structure on the project and you all deserve a lot of credit for this milestone. It was not only a pleasure to work with you all on this fabrication and hauling to site of the monstrosity but it was a privilege to have such a team behind us to make this happen with no incident and what on the surface seemed child’s play. You all should be very proud of yourselves and your collective teams and firms, without you none of this was even conceivable.”

Materials & Logistics

Cenovus Superior Refinery

“I worked with Boardman on a project involving multiple vessels. The team’s impressive knowledge of ASME Section VIII Div 1 was critical to the success of the project. I enjoyed seeing the vessels in person during an engineering design course at the Boardman facility. The team always kept me in the loop and ensured quality work from fabrication through shipment.”

Mechanical Engineer

Black & Veatch

“Boardman was great to work with from the initial bidding phase through procurement. It is clear that they value relationships and are very professional. I have worked with Boardman in the past, and they continue to meet the requirements of our projects and owners. I value our relationship and hope to continue to work with them in the future.”

Sr. Procurement Manager

Black & Veatch

“Thank you for the high level of communication on this project and the effort put into making things work. So far this project has gone smoothly and our efforts have not gone unnoticed. Specifically the time invested in making sure the anchor bolt pattern matched their existing foundation. Not sure if it is my place to say but you are highly regarded at this refinery.”

Mechanical Engineer

Merrick Engineering

“I am continually impressed with the level of quality and professionalism on this project from the beginning.”

Inspector

HF Sinclair

“Boardman was very professional throughout the engineering and design of this vessel. They did a really good job on fabrication.”

Project Manager

Chevron Phillips Chemical